Widening & Strengthening of Bihar–Devri–Raniganj–Kathola Road (Bihar–Babaganj Road)
₹27.73 Cr · 20 Km · PWD Pratapgarh
Project Overview
The Bihar–Devri–Raniganj–Kathola Road project involved widening and strengthening a 20-kilometre Major District Road (MDR-175E) in Pratapgarh district. The works comprised earthwork, GSB/WBM/WMM granular layers, bituminous pavement layers (PC/Seal Coat/BM/DBM/BC/SDBC), cement concrete works, and culvert/bridge construction. Total work executed was valued at ₹27.73 Crore.
Key Project Details
LocationBihar to Devri (Amehti Bardi) via Bakhri, Raniganj, Keithola, Samaspur
District / StatePratapgarh, Uttar Pradesh
Road Length20.00 Km
ClientExecutive Engineer, Construction Division-1, Public Works Department, Pratapgarh
Agreement No.01/SE-PBH-FTP Circle/2017-18 dt 19.05.2017
Tendered Cost₹27,72,96,511.00 (₹27.73 Crore)
Estimated Cost₹26,16,00,482.00 (₹26.16 Crore)
Total Work Executed₹27,72,60,349.93 (₹27.73 Crore)
Earnest Money₹1,40,65,000.00
Date of Start19 May 2017
Stipulated Completion18 May 2018
Actual Completion17 December 2019
Certified ByExecutive Engineer, Construction Division-1, Public Works Department, Pratapgarh
Scope of Work
- Widening and strengthening of state road from Bihar to Devri (Amethi Bardi) via Bakhri, Raniganj, Keithola, and Samaspur on MDR-175E
- Earthwork
- GSB/WBM/WMM granular layers
- PC/Seal Coat/BM/DBM/BC/SDBC bituminous works
- Cement concrete structural works
- Culvert and bridge construction
- Interlocking paver blocks
- Thermoplastic road marking compound
- Miscellaneous civil works
Significance
This was one of BHIPL’s earliest large-scale district road projects in Pratapgarh, establishing the company’s reputation for quality execution in the region. The project transformed rural connectivity along the Bihar–Babaganj corridor.
Bill of Quantities
| S.No. | Item Description | Unit | Quantity | Amount (\u20b9) |
|---|---|---|---|---|
| A | Earth Work | Cum | — | 70,99,160.68 |
| B | GSB/WBM/WMM & Granular Works | Cum | — | 12,04,67,227.86 |
| C | PC/Seal Coat, BM/DBM/BC/SDBC Bituminous | Cum | — | 10,39,85,889.78 |
| D | Cement Concrete Works | Cum | — | 4,04,27,943.81 |
| E | Culvert/Bridge | L.S. | — | 30,79,529.25 |
| F | Interlocking Paver Block | L.S. | — | 16,91,990.29 |
| G | Thermoplastic Compound | L.S. | — | 4,72,458.49 |
| H | Other Miscellaneous Works | L.S. | — | 36,149.78 |
| Total Value of Work Done | 27,72,60,349.93 | |||